Rekapitulasi Pengadaan Barang Jasa melalui LPSE Tahun 2011 - 2017 LPSE Kota Pangkalpinang

521

Jumlah Paket Lelang

Rp. 849 M

Jumlah Pagu Dana

Rp. 29.996 Jt

Selisih

3,61%

Efisiensi

1. INFORMASI LELANG TOTAL DARI TAHUN 2011 - 2017

DESKRIPSI TOTAL
TOTAL PAKET521 Paket
TOTAL PAKET SELESAI503 Paket
TOTAL BELUM SELESAI18 Paket
PAGU PAKET LELANG849.190.157.114
PAGU PAKET SELESAI829.863.083.251
NILAI PENAWARAN TERKOREKSI799.867.477.778
SELISIH HASIL LELANG29.995.605.473 (3,61%)

2. GRAFIK TOTAL PAKET DAN PAGU DANA DARI TAHUN 2011 - 2017

3. REKAPITULASI HASIL LELANG PERTAHUN DARI TAHUN 2011 - 2017

TAHUN PAKET LELANG
(PAKET)
PAKET LELANG
SELESAI (PAKET)
PAGU PAKET
(Rp)
PAGU PAKET LELANG
SELESAI (Rp)
NILAI PENAWARAN
TERKOREKSI (Rp)
SELISIH LELANG
(Rp)
PROSENTASE
(%)
2011 14 9 12.474.357.250 8.568.984.150 7.645.788.000 923.196.150 10,77
2012 101 95 71.139.864.492 64.987.614.492 61.346.435.081 3.641.179.411 5,60
2013 108 104 78.917.221.913 74.122.746.150 71.556.964.106 2.565.782.044 3,46
2014 76 76 74.939.892.148 74.939.892.148 72.726.243.991 2.213.648.157 2,95
2015 88 85 105.520.738.573 101.045.763.573 93.746.549.530 7.299.214.043 7,22
2016 118 118 485.380.139.014 485.380.139.014 472.649.192.070 12.730.946.944 2,62
2017 16 16 20.817.943.724 20.817.943.724 20.196.305.000 621.638.724 2,99
Jumlah Total : 521 503 20.817.943.724 20.817.943.724 20.196.305.000 621.638.724 2,99

4. REKAPITULASI HASIL LELANG BERDASARKAN JENIS PENGADAAN DARI TAHUN 2011 - 2017

JENIS PENGADAAN BARANG
JASA DAN MODAL
LELANG UMUM, SELEKSI UMUM
LELANG TERBATAS
LELANG SEDERHANA, PEMILIHAN LANGSUNG
SELEKSI SEDERHANA
TOTAL
(PAKET) (RP) (PAKET) (RP) (PAKET) (RP)
Barang 17 19.949.698.685 46 44.497.750.036 63 64.447.448.721
Konsultasi 16 16.846.376.000 9 1.002.879.400 25 17.849.255.400
Konstruksi 50 387.423.479.168 352 322.836.996.814 402 710.260.475.982
Lainnya 1 256.345.000 12 7.053.952.675 13 7.310.297.675

5. GRAFIK REKAPITULASI HASIL LELANG BERDASARKAN JENIS PENGADAAN DARI TAHUN 2011 - 2017

6. DATA PAKET LELANG DENGAN NILAI PAGU 50 JT S/D 1 MILYAR

TAHUN JUMLAH PAKET(PAKET) PAGU PAKET (Rp)
2017 10 6.831.943.724
2016 58 29.358.924.094
2015 60 32.638.361.000
2014 55 24.763.731.500
2013 91 48.586.053.630
2012 85 38.366.380.792
2011 11 3.493.807.250

7. DATA PAKET LELANG DENGAN NILAI PAGU DIATAS 1 MILYAR

TAHUN JUMLAH PAKET(PAKET) PAGU PAKET (Rp)
2017 6 13.986.000.000
2016 60 456.021.214.920
2015 28 72.882.377.573
2014 21 50.176.160.648
2013 17 30.331.168.283
2012 16 32.773.483.700
2011 3 8.980.550.000

8. SEBARAN ASAL KOTA PEMENANG LELANG DARI TAHUN 2011 - 2017

NAMA KOTA JUMLAH PAKET NILAI KONTRAK
Pangkal Pinang (Kota) 335 Paket 365.596.146.342
Bangka (Kab.) 75 Paket 90.937.567.250
Luar Bangka Belitung 70 Paket 321.663.975.020
Bangka Barat (Kab.) 9 Paket 9.105.050.166
Belitung (Kab.) 5 Paket 7.323.331.000
Belitung Timur (Kab.) 4 Paket 2.163.116.000
Bangka Selatan (Kab.) 4 Paket 2.947.043.000
Bangka Tengah (Kab.) 1 Paket 131.249.000

9. GRAFIK SEBARAN ASAL KOTA PEMENANG LELANG DARI TAHUN 2011 - 2017

10. REKAPITULASI HASIL LELANG PER SKPD DARI TAHUN 2011 - 2017

NAMA SKPD TAHUN PAKET LELANG
(PAKET)
PAKET LELANG SELESAI
(PAKET)
PAGU PAKET
(Rp)
PAGU PAKET LELANG
SELESAI (Rp)
HASIL LELANG
(Rp)
SELISIH LELANG
(Rp)
(%)